Foreign investors may participate in Philippine renewable energy projects, but the permitted level of foreign ownership depends on the project’s precise activity and legal structure. A distinction must be made between owning or operating a power-generation facility and undertaking the exploration, development, production, or utilization of natural resources under a renewable energy service or operating contract.

The Department of Energy’s Revised Omnibus Guidelines govern the award and administration of renewable energy contracts and the registration of renewable energy developers. They do not, by themselves, remove constitutional nationality restrictions applicable to natural-resource utilization or authorize foreign ownership in every renewable energy activity.

Accordingly, the statement that solar, wind, and biomass ventures are uniformly open to 100% foreign ownership requires qualification. The answer depends on whether the project involves an RE service or operating contract, a power-generation business, or another regulated activity.

Governing Renewable Energy Laws

Republic Act No. 9513 defines renewable energy resources to include biomass, solar, wind, geothermal, ocean energy, and hydropower that conforms with applicable standards. It also recognizes renewable energy systems that convert these resources into useful forms of energy ([Renewable Energy Act of 2008](#lNUmYJxOWMEW.10); [Renewable Energy Act of 2008](#lNUmYJxOWMEW.11)).

The Renewable Energy Act authorizes the government to award renewable energy service or operating contracts for the exploration, development, production, or utilization of renewable energy resources. These contracts remain subject to Article XII, Section 2 of the 1987 Constitution when the activity involves natural-resource utilization ([Renewable Energy Act of 2008](#mA-uaWqBSd1R.2)).

The constitutional restriction is significant because the exploration, development, and utilization of natural resources may be undertaken through arrangements involving Filipino citizens or corporations or associations at least 60% of whose capital is owned by Filipinos ([Opinion No. 19-24](#mA-uaWqBSd1R.1)).

Are Solar, Wind, and Biomass Projects Fully Foreign-Owned?

Not automatically. Full foreign ownership cannot be stated as a universal rule for all solar, wind, and biomass projects based only on the technology used.

A renewable energy developer applying for an RE service or operating contract must comply with the constitutional nationality rule when the project involves the exploration, development, production, or utilization of natural resources. The SEC has described this category as subject to a 60% Filipino and 40% foreign-equity limit under the applicable constitutional and foreign-investment rules ([Opinion No. 19-24](#mA-uaWqBSd1R.1); [Opinion No. 19-24](#mA-uaWqBSd1R.2)).

The ownership analysis may be different for an enterprise that merely constructs or provides services to a power project. The SEC has recognized that a 100% foreign-owned domestic corporation may engage in constructing power plants for energy companies when the activity does not itself fall within a restricted category or require a public-utility franchise under the applicable law ([Opinion No. 09-23]).

Thus, the investor must distinguish the following:

Project activityForeign-equity inquiry
RE service or operating contract involving natural-resource utilizationSubject to the constitutional and statutory nationality rules, including the 60% Filipino ownership requirement identified by the SEC
Power generation using solar, wind, or biomassRequires review of the precise activity, applicable DOE rules, the Foreign Investment Negative List, and any public-utility or public-service classification
Construction of a power plant for another energy companyMay be open to 100% foreign ownership if the contractor is not itself undertaking a restricted activity or operating a public utility
Ownership or operation of a transmission or distribution facilityRequires separate review of constitutional, public-utility, franchise, and sectoral restrictions

Renewable Energy Service and Operating Contracts

Under the Renewable Energy Act, the State retains ownership and control over forces of potential energy and other natural resources, including kinetic energy from water, marine currents, and wind, and thermal energy from solar, ocean, geothermal, and biomass sources ([Opinion No. 19-24](#mA-uaWqBSd1R.2)).

The State may directly undertake renewable energy activities or enter into the legally recognized service, operating, joint-venture, or production-sharing arrangements. Foreign renewable energy developers may participate through an RE service or operating contract, but the participation remains subject to Article XII, Section 2 of the Constitution ([Opinion No. 19-24](#mA-uaWqBSd1R.2)).

The SEC applied this principle to a biomass power plant seeking conversion of its Provisional Authority to Operate into a Certificate of Compliance as a feed-in-tariff-eligible plant. The ownership issue was evaluated under the 60% Filipino and 40% foreign rule ([Opinion No. 19-24](#mA-uaWqBSd1R.0]).

How Is Filipino Ownership Measured?

For a corporation claiming Filipino nationality in a partly nationalized activity, the Foreign Investments Act generally requires at least 60% of the outstanding capital stock entitled to vote to be owned and held by Philippine citizens ([Opinion No. 19-24](#mA-uaWqBSd1R.1)).

The relevant inquiry is not limited to the nominal classification of shares. Filipino ownership must be genuine, and the analysis must consider voting rights, beneficial ownership, and control.

SEC Memorandum Circular No. 8, Series of 2013, adopts a two-tiered method for determining compliance with the 60% Filipino ownership requirement. The Grandfather Rule is applied when there is doubt about the location of beneficial ownership and control ([Opinion No. 19-24](#mA-uaWqBSd1R.0]).

The SEC has also stated that shares entitled to vote in the election of directors must be considered in calculating Filipino interest, regardless of share class or par value. Legal and beneficial ownership must both be examined ([Opinion No. 11-44](#c8Z1D6rX7oGx.8)).

Why Beneficial Ownership Matters

A corporation cannot rely on Filipino names appearing in its stock and transfer records if the real economic ownership and voting control belong to foreign investors.

The two-tiered nationality analysis seeks to determine whether the apparent Filipino ownership reflects genuine Filipino ownership. If the direct ownership structure creates doubt about beneficial ownership or control, the Grandfather Rule may trace ownership through the corporate layers ([Opinion No. 19-24](#mA-uaWqBSd1R.0]).

Project proponents should therefore review:

  • The nationality of direct and indirect shareholders;
  • The shares entitled to vote in director elections;
  • The source of funds used to acquire the shares;
  • The identity of the beneficial owners;
  • The economic benefits received by Filipino and foreign shareholders;
  • Voting agreements and shareholder arrangements; and
  • Board nomination and election procedures.

Board procedures must not dilute the proportional representation of Filipino shareholders or allow foreign investors to obtain control beyond their lawful participation ([Opinion No. 11-44](#c8Z1D6rX7oGx.8)).

Foreign Participation in Project Management

Foreign ownership and foreign management are separate questions. Even when a corporation satisfies the 60% Filipino ownership threshold, foreign nationals may be restricted from serving in management positions in a partly nationalized activity.

The SEC has stated that foreigners may not be elected as president or placed in other management positions in corporations engaged in partly nationalized activities, including renewable energy, when the arrangement would circumvent the Anti-Dummy Law ([Opinion No. 16-29]).

The Anti-Dummy Law addresses not only nominal ownership but also foreign intervention in the management, operation, administration, or control of a nationalized activity. A compliant equity ratio does not automatically authorize foreign control of the business.

Does Power-Plant Construction Have the Same Restriction?

Not necessarily. The construction of a power plant is not automatically equivalent to the exploration, development, production, or utilization of renewable energy resources.

The SEC has recognized that a 100% foreign-owned domestic corporation may engage in constructing power plants for energy companies when the activity is not included in the Foreign Investment Negative List and does not require a public-utility franchise under the applicable build-operate-transfer rules ([Opinion No. 09-23]).

The contractor’s actual functions remain controlling. A foreign-owned construction company may be treated differently from an entity that owns, operates, or manages the power-generation facility or holds the RE service or operating contract.

DOE Revised Omnibus Guidelines

The DOE Revised Omnibus Guidelines integrate existing policies for awarding and administering RE contracts and registering renewable energy developers. The issuance is intended to provide a consolidated process for renewable energy projects, including project applications, contract administration, and developer registration ([Memorandum Circular No. 2026-032](#cBrN0kCfZbv0.4)).

The DOE Guidelines should be read together with the Constitution, the Renewable Energy Act, the Foreign Investments Act, the Foreign Investment Negative List, environmental laws, local-government requirements, and energy-sector regulations.

Administrative guidelines may prescribe the procedure for awarding an RE contract, but they cannot enlarge foreign-ownership rights beyond those authorized by the Constitution and statutes.

Feed-In Tariff and Ownership

The Renewable Energy Act mandates a feed-in tariff system for electricity produced from wind, solar, ocean, run-of-river hydropower, and biomass. The system includes priority connection, priority purchase and transmission, and payment for eligible electricity, with fixed tariff rates applied for a period of not less than 12 years ([Renewable Energy Act of 2008](#lNUmYJxOWMEW.14); [Foundation for Economic Freedom v. Energy Regulatory Commission, et al.](#EK06xdwngmnA.61)).

Feed-in tariff eligibility does not itself establish that a project may be 100% foreign-owned. Ownership and FIT eligibility are separate issues. A project may qualify for a FIT arrangement only after satisfying the applicable technical, regulatory, and contractual requirements, while its corporate nationality must still comply with the Constitution and foreign-investment rules.

The Supreme Court upheld the validity of the FIT and Renewable Portfolio Standard mechanisms, including the FIT Allowance collected from consumers. It held that the delegation to the DOE and ERC was valid because the Renewable Energy Act provided sufficient standards and boundaries for implementation ([Foundation for Economic Freedom v. Energy Regulatory Commission, et al.](#EK06xdwngmnA.79)).

The Court also recognized the FIT Allowance as a valid exercise of police power rather than an unconstitutional tax, because it was reasonably related to the State’s legitimate objective of accelerating renewable energy development ([Foundation for Economic Freedom v. Energy Regulatory Commission, et al.](#EK06xdwngmnA.95)).

Offshore Wind and Environmental Approvals

Foreign-equity compliance is only one part of project approval. Offshore wind projects must also consider environmental requirements under the Philippine Environmental Impact Assessment System.

DENR Administrative Order No. 2024-02 provides interim guidelines for environmental compliance certificates for offshore wind energy projects. The guidelines address environmental assessment and mitigation measures for offshore wind development ([Memorandum Circular No. 2026-032](#cBrN0kCfZbv0.4)).

A foreign-owned or partly foreign-owned project must therefore obtain the required environmental and energy approvals even if its ownership structure is permissible.

Renewable Energy Projects in Protected Areas

Renewable energy projects located in protected areas may be subject to additional restrictions. Under the Mts. Banahaw-San Cristobal Protected Landscape Act, renewable energy projects in the protected landscape require an act of Congress, except for energy from wind, sun, and water sources and mini-hydropower projects not exceeding three megawatts, subject to location, technology, environmental, and Protected Area Management Board conditions ([Mts. Banahaw-San Cristobal Protected Landscape Act of 2009](#H7O4gnPNHq9P.43)).

The project must be outside the strict protection zone, use reduced-impact technologies, undergo the environmental impact assessment system, and obtain PAMB endorsement. A foreign-equity analysis cannot replace these protected-area requirements.

Compliance Checklist for Foreign Investors

  1. Identify whether the investment concerns power generation, an RE service or operating contract, construction, transmission, distribution, or another activity.
  2. Determine whether the activity involves the exploration, development, production, or utilization of natural resources.
  3. Review the current Foreign Investment Negative List and sector-specific restrictions.
  4. Apply the 60% Filipino ownership rule where the activity falls within a constitutionally restricted natural-resource arrangement.
  5. Trace direct and indirect ownership when beneficial ownership or control is uncertain.
  6. Review voting rights and board nomination arrangements.
  7. Confirm whether foreign nationals may serve as directors, officers, or managers.
  8. Obtain the appropriate DOE RE contract or registration.
  9. Secure ERC, environmental, local-government, grid, and other required approvals.
  10. Check whether the project is located in a protected area or another specially regulated zone.

Illustrative Examples

Solar power-generation company. A foreign investor proposes to own a solar-generation company. The investor must determine whether the project involves a restricted RE service or operating contract, whether it is subject to a public-utility or public-service rule, and whether the current foreign-investment regulations permit the proposed ownership structure.

Biomass project with an RE contract. A corporation applying for an RE service or operating contract for a biomass power plant must demonstrate compliance with the constitutional Filipino-equity requirement when the project involves natural-resource utilization. A 100% foreign-owned structure cannot be assumed to be valid merely because biomass is a renewable resource.

Foreign construction contractor. A 100% foreign-owned corporation constructs a solar power plant for an independently owned Philippine energy company. If it performs only construction services and does not own, operate, manage, or hold the RE contract for the facility, it may fall within the SEC-recognized construction exception, subject to the exact business activity and applicable permits.

Wind project in a protected area. A wind project may benefit from the protected-area exception for energy from wind, but it must still satisfy the location, capacity, reduced-impact technology, environmental assessment, and PAMB-endorsement requirements applicable to the protected landscape.

Conclusion

Foreign equity in Philippine renewable energy projects cannot be determined solely from the project’s technology. Solar, wind, and biomass projects must be classified according to the activity actually performed and the authority under which the project operates.

Where the project involves an RE service or operating contract for the exploration, development, production, or utilization of natural resources, the 60% Filipino ownership requirement identified in the Constitution and the applicable SEC guidance remains relevant ([Renewable Energy Act of 2008](#mA-uaWqBSd1R.2); [Opinion No. 19-24](#mA-uaWqBSd1R.1)). The ownership analysis must consider voting rights, beneficial ownership, indirect ownership, and actual control.

Some activities, such as construction of power plants for energy companies, may be open to 100% foreign ownership when they do not themselves involve a restricted activity or public-utility franchise ([Opinion No. 09-23]). That conclusion is activity-specific and does not automatically apply to ownership or operation of the renewable energy facility.

Investors should obtain a project-specific nationality assessment, review the DOE Revised Omnibus Guidelines and current Foreign Investment Negative List, document beneficial ownership, and secure all energy, environmental, grid, local-government, and protected-area approvals before investing or commencing operations.

About Nicolas and De Vega Law Offices

 Nicolas and de Vega Law Offices is a full-service law firm in the Philippines.  You may visit us at the 16th Flr., Suite 1607 AIC Burgundy Empire Tower, ADB Ave., Ortigas Center, 1605 Pasig City, Metro Manila, Philippines.  You may also call us at +632 84706126, +632 84706130, +632 84016392 or e-mail us at [email protected]. Visit our website https://ndvlaw.com.